Friedrich Vorwerk wins contract to build H2Coastlink 1 hydrogen pipeline in northwest Germany

German energy infrastructure specialist Friedrich Vorwerk Group has secured a major contract, as part of a joint venture, to build the H2Coastlink 1 hydrogen pipeline between Emden and Leer in Lower Saxony, a project that forms part of the Clean Hydrogen Coastline programme and will link EWE Hydrogen’s 320 MW electrolyser under construction at Emden-Borssum to Germany’s national hydrogen core network.
The contract was awarded by EWE NETZ GmbH acting as general contractor on behalf of GTG Nord GmbH, the designated transmission system operator.
The pipeline, valued in the tens of millions of euros, covers approximately 24 km of new DN 400 high-pressure hydrogen infrastructure, including a connecting pipeline from the future electrolyser to an injection facility in Emden and connections to the supra-regional network in Leer, where it will tie into Gasunie Deutschland’s HyPerLink backbone. Preparatory work is scheduled to begin in summer 2026, with the pipeline expected to be commissioned and handed over to GTG Nord in autumn 2027.
The route will cross approximately 90 obstacles, including ecologically sensitive zones and water bodies, using methods including horizontal directional drilling.
Friedrich Vorwerk said the scale of ongoing work connecting new hydrogen and power plant sites to the network, combined with Germany’s plans to complete a 9,000-km hydrogen core network, is driving a sustained increase in demand for its pipeline construction services.