Entropy launches CCS project delivering low-carbon power in Alberta

Entropy Inc. has commissioned its Glacier Phase 2 project in Alberta, Canada, combining natural gas power generation with carbon capture and storage (CCS) to deliver low-carbon electricity and reduce emissions from industrial operations.
The project, located at Advantage Energy’s Glacier Gas Plant in Saddle Hills County, integrates a 15 MW gas turbine with carbon capture, transportation and storage infrastructure covering both the new power generation facility and approximately 30 MW of existing gas-fired compression engines.
Entropy said the project represents a first-of-its-kind deployment of post-combustion carbon capture technology on a gas turbine used for power generation. The facility builds on earlier carbon capture systems operating at the site since 2022 and brings total integrated CCS capacity at Glacier to 45 MW.
The combined system is designed to capture up to 192,000 tonnes of carbon dioxide (CO₂) annually from 11 gas-fired engines and one power generation turbine, with targeted capture rates of more than 90% for major unabated emissions sources at the site.
Sanjay Bishnoi, Chief Executive Officer of Entropy, said the project would provide reliable low-carbon power for Advantage’s operations while also supplying electricity to Alberta’s grid through the Alberta Electric System Operator (AESO) market.
A 15 MW Solar T130 turbine has been installed as part of the project, with electricity supplied to Advantage under a 15-year power purchase agreement covering 6 MW at a price of $85 per megawatt-hour. According to Entropy, a third-party engineering assessment calculated the design-basis carbon intensity of the electricity at 84 kg of CO₂ per megawatt-hour using a lifecycle assessment approach.
The company said all major construction activities have been completed and the facility has entered steady-state commissioning. Verified performance data is expected to be published in the coming months through EntropyIQ, the company’s carbon measurement and accounting platform designed to track captured CO₂ from emissions sources through to permanent storage.
James Martin, Chief Operating Officer at Entropy, said collaboration with suppliers and Advantage helped the company complete plant interconnections during a scheduled three-week turnaround at the Glacier facility without affecting daily operations.
The Global CCS Institute said the project demonstrates the potential for carbon capture technology to support reliable low-carbon electricity generation as demand grows for firm power with lower emissions.
Jarad Daniels, Chief Executive Officer of the Global CCS Institute, said Glacier Phase 2 showed that CCS could provide a scalable solution for reducing emissions while maintaining competitiveness in energy-intensive industries.
Entropy said the project’s development has been supported by Canadian carbon capture policies, including the federal Carbon Capture, Utilisation and Storage Investment Tax Credit (CCUS ITC), Alberta’s Carbon Capture Utilisation and Storage Investment Program (ACCIP) and local incentives from Saddle Hills County.
The company has invested more than $250 million across several CCS projects in Canada and said timely approval and administration of government support programmes will be important for future carbon capture investment.
Entropy said delays in accessing CCUS incentives have increased financing costs and reduced certainty for developers and investors, adding that predictable policy implementation will be critical as Canada seeks to expand large-scale carbon capture deployment.
The Glacier Phase 2 project comes as industries across North America explore carbon capture as a way to reduce emissions from natural gas power generation and industrial processes where direct electrification remains challenging.